A project manager received several complaints from different project team members related to an unnecessary additional step the functional lead implemented as a preference. The project team members' work has been affected by this and they have missed a few deadlines.
What should the project manager do to address this concern?

الخيارات

  • A Advise the team that the functional lead's preference should be taken into consideration.
  • B Document the additional step from the functional lead and adjust the timelines to accommodate the change.
  • C Recommend the functional lead meet with the project team members to convince them to accept the change.
  • D Ask the functional lead to remove this additional step as it is not vital to the project.