السؤال 494 من 874

كل الأسئلة

A project manager coordinates several projects in one program. Each project concerns a different country, has a different sponsor, and has specific business priorities. The resources are shared among the projects. The project manager anticipates this could result in delays and/or conflicts that will affect the program outcomes.
What should the project manager do to prevent such a situation?

الخيارات

  • A Review all project schedules and add a 3-month time period to each to cover such a risk and ensure there will be no delay that could affect the program.
  • B Organize regular meetings to identify risks related to the projects and program, assess them, and define action plans when needed to mitigate the risks.
  • C Ask each project manager to write a detailed weekly report listing all the activities, what was achieved, what needs to be done, and the identified risks.
  • D Ask the project managers to work on their own schedules independently of one another and aggregate these schedules to present at the monthly steering committee meeting.