A project manager is leading a complicated project that requires integrating several components from different suppliers. During execution, the project team indicates that some components are not being delivered to the site on time, affecting the project schedule.
What should the project manager do to address this concern?

الخيارات

  • A Review the project schedule with project team members and the suppliers.
  • B Advise the procurement department to develop a new supplier strategy.
  • C Use the procurement and risk management plans to manage this issue.
  • D Register the issue as a risk with the project team members.