A project manager was recently assigned to work on a hybrid project. After being a part of the project team for a couple of months, the project manager realizes that parts of this project depend on other organizational projects. These dependencies have not been identified.
What should the project manager do first?

الخيارات

  • A Brainstorm with the team and stakeholders to identify the risks.
  • B Review the risk register and update it if necessary.
  • C Ignore the concerns for now and review them in 3 months.
  • D Host a retrospective session with the agile team.