The project team completed a demonstration of the main deliverable of the project. Although the project sponsor is happy with the outcome and is ready to sign the release to production, one of the business unit managers who attended the demo believes that the deliverable is not complete.
Which document should the project manager use to resolve this situation?

الخيارات

  • A Requirements management plan
  • B Requirements traceability matrix
  • C Risk management plan
  • D Project scope statement