An agile team is funded for a fixed 6-month period. The sponsor's request will take at least 12 months to complete.
What should the project manager do?

الخيارات

  • A Prioritize the scope items to determine the duration needed for a minimal viable product (MVP) and adjust the funding request.
  • B Have the team work on the list of requests from the sponsor without modification until the 6-month period ends.
  • C Request the team complete all scope items, with the assumption of securing additional funding within 6 months.
  • D Inform the sponsor that the team is unable to complete the requests due to a lack of funding, and defer the project.