اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 442 من 874

كل الأسئلة

A project manager has just started a project to build an external web application for customers to track their orders. The project is expected to take 2 years to complete. Customers are very dissatisfied with the time line and demand the project be completed in 1 year.
What should the project manager do to improve delivery?

الخيارات

  • A Ask the sponsor for additional resources and funding to speed up the work and cover additional labor costs.
  • B Review the work packages, schedule, and estimates with the team and consolidate tasks to shorten the schedule.
  • C Review work packages with the team to build a new incremental delivery plan with multiple releases and obtain the customers' feedback.
  • D Schedule more frequent design reviews with the customers and provide prototypes to demonstrate progress and gather feedback.