اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 423 من 874

كل الأسئلة

A product owner is complaining about the team's performance. The developers are highly skilled, and most of the issues were caused by dependencies. The developers provide a formal status report every day, but it is clear that the other team members are not satisfied with this.
What should the project lead do?

الخيارات

  • A Ask the developers to use peer programming.
  • B Ask the product owner to reprioritize the backlog.
  • C Build a detailed schedule and describe each task in detail.
  • D Build a task board on a large wall using sticky notes.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.