During the execution of a project, a project manager is informed that a team member is leaving the company. What should the project manager do next?

الخيارات

  • A Freeze the activities of the lost resource until they are replaced.
  • B Ask the project sponsor to replace the resource immediately.
  • C Record the situation in the issue log immediately and evaluate the impact of losing the resource.
  • D Wait for the next project status meeting to evaluate the impact of one less resource.