A project is starting its first iteration out of six. During one of the daily meetings, the project manager realized that one of the team members does not have experience working in agile environments.
What should the project manager do?

الخيارات

  • A Ask the sponsor for additional budget for training.
  • B Assign an agile mentor and follow the training process.
  • C Ask to increase the capacity of the team to finish on time.
  • D Give the team member some time to learn agile practices.