A key project stakeholder recently joined the project and is questioning some of the previously made decisions. This starts to impact project execution.
What should the project manager do?

الخيارات

  • A Reach out to the stakeholder via phone to explain that all decisions have been agreed upon with their predecessor.
  • B Update the risk register with a new risk of potential project changes as a result of stakeholder misalignment.
  • C Schedule a meeting with the stakeholder to provide an overview of the project, including the agreed-upon decisions.
  • D Provide the stakeholder with a link to a file-sharing site where the supporting documents for decisions are filed.