A scrum master is receiving conflicting status updates for the same task. How should an accurate status be obtained from the team?

الخيارات

  • A Assign one person to be responsible for the task.
  • B Review the deliverable carefully and determine the right status.
  • C Encourage team members to work together.Encourage team members to work together.
  • D Establish a clear definition of done (DoD) for each task.