A project manager is assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.
Which first two actions should the project manager perform? (Choose 2)

الخيارات

  • A Discuss the possible impacts with subject matter experts (SMEs).
  • B Ask the project sponsor for additional budget for contingency.
  • C Consult with the project stakeholders and evaluate the impact.
  • D Create a change request to discuss with the change control board (CCB).
  • E Perform a risk identification process with the project team.