A project is continuously overlapping phases. Due to a recent human error, the team, which is made up of senior members, is experiencing distrust issues from other departments and lacking initiative. This is impacting overall performance and putting the project objectives at risk.
What should the project manager do when executing the next sprint?

الخيارات

  • A Explain high-level objectives and ask team members to self-organize around their tasks to meet the objectives.
  • B Request offsite team-building activities and deploy incentive plans around their tasks.
  • C Coach those responsible for the error so that the whole team understands they are not responsible for it.
  • D Identify the poor performers and ask their functional managers to assign them a mentor.