During project execution, a key stakeholder approaches the project manager and questions the business value of the project. What should the project manager do?

الخيارات

  • A Validate the business value with the stakeholder by ensuring each requirement is still aligned to the business and project objectives.
  • B Inform the stakeholder that the project will still proceed to completion because the project charter has already been approved.
  • C Consult the remainder of the stakeholders and the sponsor to determine if they have the same concern.
  • D Explain to the stakeholder that it is up to the project sponsor and the client to determine if the project still has the perceived business value.