A project manager is managing a project that is using three Scrum teams for development. The sprint increments are integrated into a single package that is then tested by a specialized testing team. The test lead does not want to approve the deployment, although the developers met the definition of done (DoD).
What should the project manager do to align the expectations of various teams?

الخيارات

  • A Review the user stories template before the next sprint planning.
  • B Discuss the issue with the sponsor and ask for a resolution.
  • C Discuss the issue with the development and test managers.
  • D Review the acceptance criteria with the entire project team.