A company has decided to create a new product to prepare itself for the changing economy. The technology required for the new product is not well understood yet, and the requirements are still being debated.
Which approach should the project manager advise for this project?

الخيارات

  • A Agile
  • B Hybrid
  • C Lean
  • D Predictive