The velocity of the team is decreasing at every iteration. The project team members are complaining that the user stories are being rejected by the quality assurance team.
Which three actions should the project manager take? (Choose three)

الخيارات

  • A Negotiate with the teams involved to manage team dependencies.
  • B Elaborate on the plan to implement a solution and execute it.
  • C Conduct a root cause analysis (RCA) and identify a solution.
  • D Increase the working time to recover the lost time.
  • E Evaluate the effectiveness of the proposed solution.