A project manager is working in a regulated industry. The minimum viable product (MVP) for the launch has been defined. The project manager learns that the regulatory body requires a prototype for inspection before the product can be launched; however, the prototype is not part of the MVP definition.
What should the project manager do next?

الخيارات

  • A Create an MVP that contains the scope for the prototype and that will be prioritized with the compliance team.
  • B Speak with the product manager to prioritize the compliance-related activities high enough in the backlog to submit a prototype to the regulatory body.
  • C Identify the missing requirements, prioritize the missing compliance work directly into the backlog, and assign the work to the team.
  • D Reschedule the launch of the product until the team can produce a prototype for inspection as required by the compliance team.