اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 367 من 874

كل الأسئلة

Following an investment decision-making meeting for a project, a change to the organizational structure takes place in a multinational company. Due to the organizational change, internal stakeholders are referring the project manager to various other personnel for approval of the project budget.
What should the project manager do to obtain approval of the project budget?

الخيارات

  • A Approach each of the referred individuals separately and request approval of the project budget from the appropriate person.
  • B Identify the right person with help from local management, present the project summary, and request budget approval.
  • C Obtain the latest organizational chart and send an email to the appropriate person requesting budget approval.
  • D Provide the decision executive with all of the project details and request budget approval from the appropriate person.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.