An email arrives shortly after the beginning of a sprint. It is from a key project stakeholder who is unfamiliar with agile approaches and has a serious complaint about future work that has been scheduled. The stakeholder is insisting that a future work package be removed from the backlog entirely, claiming that it is unnecessary.
What should the project manager do?

الخيارات

  • A Invite the stakeholder to the backlog refinement meeting to discuss their request.
  • B Alter the backlog to accommodate the stakeholder's request.
  • C Discuss the stakeholder's request at the next retrospective meeting.
  • D Address the stakeholder's request at the daily standup and ask for the team's opinion.