A project manager is managing a project that will engage resources from multiple countries in different time zones. What should the project manager do to ensure that team members are effective?

الخيارات

  • A Schedule meetings every 2 days at the same time with all team members.
  • B Organize a daily meeting for all team members and extend it, if required.
  • C Schedule meetings every 2 days that align with team members' time zones.
  • D Organize a standard meeting time to engage all of the team members.