اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 316 من 874

كل الأسئلة

During a project’s third iteration, two of the existing team members were replaced. As the project entered the next iteration, the team velocity dropped and the performance started to slip.
What should the project manager do?

الخيارات

  • A Convene a team building event to address key performance indicators (KPIs).
  • B Discuss the decrease in productivity with human resources (HR).
  • C Guide the team to revert back to the forming and storming stages.
  • D Escalate the issue to the project sponsor.