After completion of a project with specific users in various countries, the project manager's supervisor asks if the project users are satisfied with the way the project was run. What two actions should the project manager take? (Choose 2)

الخيارات

  • A Refer to the communications management plan.
  • B Send a questionnaire to the project participants and seek their feedback.
  • C Obtain official approval on the new process from the various countries.
  • D Deliver the project materials to the users and see if they have any comments.
  • E Prepare the lessons learned from the project phase.