A project manager is responsible for building a bridge. The high-level elements of the project are handled using a predictive approach. The software responsible for retracting the bridge has been developed based on agile principles. During software development, the workflow is often interrupted by various delays or impediments due to lack of information.
How should the project manager handle this situation?

الخيارات

  • A Apply lean manufacturing to limit the team’s work.
  • B Increase retrospectives to deliver results fast.
  • C Incorporate small batches of work into the project.
  • D Make work visible using Kanban boards.