During the planning stage of a project the project manager realizes that a standard stakeholder engagement approach will not suffice. One of the client representatives, who is not a key decision maker, is extremely opinionated. This client representative could become a roadblock to progress due to their perceived level of authority during meetings.
How should the project manager handle this moving forward?

الخيارات

  • A Update the risk register to consider the possible project impacts.
  • B Allocate time to gain buy-in from the stakeholder prior to key decision meetings.
  • C Update the project schedule to cater to this particular stakeholder.
  • D Ask that only key decision makers attend the project meetings.