A team has been struggling with various issues during the course of an iteration. The project lead facilitates a discussion of the issues and the team forms new team agreements. During the next iteration, some of the same issues appear again.
What should the project lead do next?

الخيارات

  • A Let the team self-organize and determine the best means to prevent the issues from occurring again.
  • B Post the agreements in a conspicuous place where all of the team members can see them.
  • C Challenge the team to determine if the issues surfaced again because agreements were not followed.
  • D Notify senior management of the issues, and have them review the importance of agreements with the team.