اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 221 من 874

كل الأسئلة

A project manager for a strategic initiative realizes a new stakeholder is interested in the project and wants to ensure the stakeholder is fully aware of the goals, objectives, benefits, and risks of the project. What should the project manager do to enhance the success of the project?

الخيارات

  • A Schedule a meeting with the new stakeholder.
  • B Share the project status reports with the new stakeholder.
  • C Add the new stakeholder to the communications management plan.
  • D Update the stakeholder engagement plan.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.