The resource management plan is already done, and the team is located in different countries around the world. Team members are in multiple time zones, and they use different languages for communication. The project manager needs to keep the team organized and avoid misunderstandings and miscommunication that may produce a negative impact to the project.
What should the project manager do to reduce negative impacts to the project?

الخيارات

  • A Conduct a multigenerational management training session.
  • B Hold a virtual meeting to discuss the political environment.
  • C Conduct cultural awareness seminars.
  • D Modify the communications management plan to account for regional differences.