While managing a project, the project manager has just noticed that the last several monthly invoices have been challenged by the client when they were clearly defined. The actual invoice payments received have also been late and were outside of the contracted payment schedule. Recent invoices have only been partially paid.
What should the project manager do?

الخيارات

  • A Hold a meeting with the client to address the issue.
  • B Review past projects for payment-related lessons learned.
  • C Conduct a meeting with the project team to update the procurement management plan.
  • D Add nonpayment to the issue log and keep tracking payments.