اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 185 من 874

كل الأسئلة

During the implementation stage of a project, a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project.
What should the project manager do?

الخيارات

  • A Inform the project sponsor about the possible delay.
  • B Provide mentoring to the newly appointed team leader.
  • C Ask the human resources (HR) director to appoint a senior team leader.
  • D Directly manage the project team to avoid project delays.