A project manager is leading an in-house company project in its very early stages. This current project is similar to another project that ended a year ago.
What should the project manager do to analyze the involved stakeholders?

الخيارات

  • A Use lessons learned from the previous project as a guide for the current project's stakeholder register.
  • B Refer to the stakeholder register from the previous project as it was similar to the current project.
  • C Document in the risk register that the current project may have different stakeholders than the previous project.
  • D Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project.