اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 183 من 874

كل الأسئلة

A project team has recently completed the initial sprint for developing an automated payroll system for a company. The project manager has scheduled a sprint planning meeting with the product owner and team members to discuss which features should be worked on next.
Which two pieces of information does the project manager need in order to make this meeting productive and effective? (Choose 2)

الخيارات

  • A Product backlog
  • B Company mission and vision
  • C Sprint goal
  • D Burndown chart
  • E Sprint charter
  • F Product backlog
  • G Company mission and vision
  • H Sprint goal
  • I Burndown chart
  • J Sprint charter