اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 182 من 874

كل الأسئلة

A company that is heavily focused on delivering projects using predictive approaches on-boards a new project manager who uses hybrid approaches. The scope of the project contains a number of unclear requirements.
How should the project manager plan the delivery of the project?

الخيارات

  • A Break down the requirements and prioritize the requirements into iterative work packages.
  • B Escalate the issue of unclear requirements to the management team and wait for final authorization.
  • C Ignore the unclear requirements and focus on the delivery plan of the project.
  • D Wait for the requirements to be more clear before any further action is taken on the project.

النقاشات