An agile project is running its fifth iteration out of eight. After the last iteration planning, the team was informed that there is a new competitor in the market, and it is necessary to move faster to ensure market share is not missed.
What should the project manager do?

الخيارات

  • A Add the competitor's functionalities to the product backlog to improve the product.
  • B Ask the sponsor to add more people to the team.
  • C Help the team to find a new approach to launch the product as soon as possible.
  • D Ask the team to increase the velocity to launch the product as soon as possible.