During project initiation, a project manager needs to identify goals and deliverables that should be completed
by the end of the project and also meet certain cost and time factors. Which of the following would best align
with these needs?

الخيارات

  • A Work breakdown structure
  • B Change log
  • C Project success criteria
  • D Milestone chart