A project manager joins an existing project. One project stakeholder is unhappy with the frequency and types of project updates received and has made a request for more information to be shared.
What should the project manager do next?

الخيارات

  • A Consult the scope baseline document to track project updates.
  • B Inform the stakeholder to wait for the annual stakeholder review meeting.
  • C Update the project communications management plan immediately.
  • D Schedule a meeting with the stakeholder to better understand their request.