A project has recently kicked off. The project manager observes that there are different expectations among the project team members. These growing misunderstandings are affecting team productivity.
Which document should the project manager use as a guide to resolve the issue?

الخيارات

  • A Project charter
  • B Stakeholder register
  • C Project organization charts
  • D Team charter