A project manager is in the middle of a project when one of the key project team members needs to take an unexpected and prolonged leave of absence. The project is ahead of schedule and running under budget.
Which two actions should the project manager take initially to resolve this problem? (Choose 2)

الخيارات

  • A Check the project’s responsibility assignment matrix (RAM) to determine which activities will be affected.
  • B Check if the team member’s activities are sufficiently documented to facilitate handover.
  • C Reassign responsibilities across the remaining members using the available float for training.
  • D Check the risk register for a prepared response to a resource being suddenly unavailable.
  • E Obtain the project sponsor’s support to replace the team member on leave.