A project team delivered a critical deliverable to the customer. The customer complained that the maintenance manual was not included.
What should the project manager do next?

الخيارات

  • A Submit a change request to include the manual.
  • B Add the needed manual and update the risk log.
  • C Review the terms and conditions of the contract.
  • D Review the stakeholder engagement plan.