A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables, which could impact the overall progress.
What should the project manager do next?

الخيارات

  • A Discuss the need to influence this stakeholder with the sponsor.
  • B Capture this in the issue log and escalate it to the project sponsor.
  • C Facilitate a brainstorming session to find potential workarounds.
  • D Meet with the stakeholder to understand what is causing the delays.