اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 99 من 874

كل الأسئلة

A project manager is working on a project nearing completion using a hybrid approach. During the last daily standup, the team identified a risk of not delivering on time because team members have not initiated any of the tasks assigned to them. The project has a hard deadline to complete the agreed-on deliverables.
What should the project manager do in this situation?

الخيارات

  • A Inform the sponsor about the degraded performance of the team members.
  • B Hire additional resources to increase capacity using the contingency budget.
  • C Reassign the remaining tasks to the most experienced team members.
  • D Empower the team to self-organize and make decisions to overcome the delay.