A new development project is about to start, and the project manager knows that a high-profile customer makes very specific and frequent requests in all sprints. This project will demand contract coordination with third parties, and the project manager must find a better way to manage customer and partner expectations.
What strategy should the project manager use?

الخيارات

  • A Specify the scope and features to be deployed in the contract clearly.
  • B Work very closely with the customer and third parties to meet their needs.
  • C Focus on the implementation of a software as a service (SaaS) solution for the customer
  • D Change the marketing and product management definitions to meet stakeholder needs.