A project involves exporting 150 packages to the customer. However, only 30 packages have been cleared by the customer for shipment. The logistics manager provided details to the customer 2 weeks ago and set up a weekly conference call to effectively communicate with them, but the customer has not been participating in the calls.
How should the project manager handle this situation?

الخيارات

  • A Find the root cause of the issue and discuss the customer's current engagement.
  • B Inform the customer that subsequent packages cannot be manufactured.
  • C Request a delivery date extension from the customer.
  • D Request a change in the contract to include the shipment in the project management plan.