A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.
Which risk management process should be performed?

الخيارات

  • A Perform Qualitative Risk Analysis, to assess the extent of the system performance impact
  • B Perform Quantitative Risk Analysis, to outline the details of the system performance issues
  • C Monitor Risks, to install system performance monitoring tools and update the risk register
  • D Plan Risk Responses, to outline the possible options to bypass the system performance issue

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.