A project team is having difficulties understanding technical details regarding requirements. The information was not initially provided by the customer, but the information is critical in the current iteration for clarification on how tasks need to be accomplished.
How should the project manager approach this situation?

الخيارات

  • A Send a burndown chart of the current sprint to the customer and seek clarifications.
  • B Request that the customer reviews and clarifies feature definitions for the current sprint.
  • C Schedule weekly meetings and product reviews with the customer to clarify requirements.
  • D Educate the customer and have them participate in daily standup meetings.