A key team member informs the project manager that they have been accepted to a master's degree program. The team member explains that the first semester of the master's program will coincide with the last phase of the project.
What should the project manager do?

الخيارات

  • A Ask the team member to inform human resources (HR) about their enrollment in the master's program.
  • B Assess the team member's commitment to the master's program and its impact on project performance.
  • C Suggest the team member postpone their enrollment in the master's program until the project is completed.
  • D Ask the team member to delegate some of their tasks to another colleague during the last phase of the project.