A project manager has noticed that the performance of a new team member has increased dramatically over the past few months... The project manager wants to formally record the team member’s success in the project documentation.
What should the project manager do?

الخيارات

  • A Record the team member's contribution in the responsibility assignment matrix (RAM).
  • B Send a communication to management recognizing the team member's contributions.
  • C Attach a note to the project management plan about the team member.
  • D Hold a project team meeting about the team member's contribution and take minutes.