A vendor has manufactured a complex product. During a factory acceptance test, several deficiencies were identified. Product delivery is on the critical path, and any delay would impact project completion.
What should the project manager do?

الخيارات

  • A Assess the schedule impact and evaluate the most feasible solution to keep the project on track.
  • B Hold the shipment until the rework is completed at the vendor's facility to eliminate extra work on-site.
  • C Initiate regular conference calls with the vendor for status updates to keep this item in focus.
  • D Ship the package as is, complete carryover work on-site, and back charge the vendor for the rework.