A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do to improve project performance?

الخيارات

  • A Address and remove obstacles and blockers for the team.
  • B Empower the team members to remove obstacles and blockers.
  • C Add blockers to the issue log and risk management plan.
  • D Ask stakeholders to communicate with the team directly.